Promulgated Rules, Decisions and Orders


Decision, ERC Case No. 2019-002 MC, In the Matter of the Application for Authority to Develop, Own, Operate and Maintain Dedicated Point - to - Point Limited Facilities to Connect to the Transmission System of National Grid Corporation of the Philippines (NGCP), Isabel Ancillary Services Co. Ltd. (IASCO) applicant
Date Docketed:7/9/2020
Published: 7/9/2020





Resolution No. 06, Series of 2020, A Resolution Approving the Adjustment to the Feed In Tariff (FIT)
Date Docketed:7/3/2020
Published: 7/3/2020



Order, ERC Case No. 2019 – 024 RC, In the Matter of the Application for Approval of the Ancillary Services Procurement Agreement Between the National Grid Corporation of the Philippines and Central Negros Power Reliability, Inc., with Prayer for the Issuance of Provisional Authority, National Grid Corporation of the Philippines (NGCP) and Central Negros Power Reliability, Inc. (CENPRI) applicants
Date Docketed:7/1/2020
Published: 7/1/2020






Resolution No. 05, Series of 2020, A Resolution Clarifying ERC Resolution No. 6, Series of 2019, entitled "A Resolution Adopting the Amendments to the Rules Enabling the Net-Metering Program for Renewable Energy"
Date Docketed:6/23/2020
Published: 6/23/2020






Resolution No. 05, Series of 2020, Annex A – Clarifications on the Amended Net Metering Rules
Date Docketed:6/23/2020
Published: 6/23/2020



Order, ERC Case No. 2019-051 RC, In the Matter of the Application for Approval of the Ancillary Services Procurement Agreement Between the National Grid Corporation of the Philippines and Prime Meridian Powergen Corporation, with Prayer for the Issuance of Provisional Authority, National Grid of the Philippines (NGCP) and Prime Meridian Powergen Corporation (PMPC) applicants
Date Docketed:5/20/2020
Published: 5/20/2020


Order, ERC Case No. 2016-163 RC, In the Matter of the Application of the National Grid Corporation of the Philippines for the Approval of Force Majeure Event Regulated FM Pass Through for Typhoon Ineng in Luzon, in Accordance with the Rules for Setting Transmission Wheeling Rates, with Prayer for Provisional Authority, National Grid Corporation of the Philippines (NGPC) applicant
Date Docketed:5/15/2020
Published: 5/15/2020



Order, ERC Case No. 2019-100 RC, In the Matter of the Application for Approval of the Ancillary Services Procurement Agreement between the National Grid Corporation of the Philippines and AP Renewables Inc. (For Makban A), with Prayer for the Issuance of Provisional Authority, National Grid Corporation of the Philippines and AP Renewables Inc. applicants
Date Docketed:5/12/2020
Published: 5/12/2020



Order, ERC Case No. 2019-101 RC, In the Matter of the Application for Approval of the Ancillary Services Procurement Agreement between the National Grid Corporation of the Philippines and AP Renewables Inc. (For Makban B), with Prayer for the Issuance of Provisional Authority, National Grid Corporation of the Philippines and AP Renewables Inc. (For Makban B) applicants
Date Docketed:5/12/2020
Published: 5/12/2020






Resolution No. 03, Series of 2020, A Resolution Extending the Deadline for Filing Applications, Pleadings and Other Documents, Allowing the Filing Thereof Through Electronic Means, and Other Matters
Date Docketed:5/8/2020
Published: 5/8/2020

12345

PROMULGATED RULES

ERC APPROVED ASPA CONTRACTS BETWEEN AS PROVIDER AND NGCP

WORKS IN PROGRESS

CaseNoTitleApplicantDate PostedDate Docketed
2019-101 RCIn the Matter of the Application for Approval of the Ancillary Services Procurement Agreement between the National Grid Corporation of the Philippines and AP Renewables Inc. (For Makban B), with Prayer for the Issuance of Provisional Authority National Grid of the Philippines (NGCP) and AP Renewables Inc. (APRI) Makban B12/27/201912/27/2019
2019-100 RCIn the Matter of the Application for Approval of the Ancillary Services Procurement Agreement between the National Grid Corporation of the Philippines and AP Renewables Inc. (For Makban A), with Prayer for the Issuance of Provisional AuthorityNational Grid of the Philippines (NGCP) and AP Renewables Inc. (APRI) Makban A12/27/201912/27/2019
2019-095 RCIn the Matter of the Application for the Approval of the Sale of Various Sub-Transmission Lines / Assets of the National Transmission Corporation (TRANSCO) to Agusan Del Sur Electric Cooperative, Inc. (ASELCO), as Covered by a Lease Purchase Agreement (LPA) dated 15 October 2019National Transmission Corporation (TRANSCO) and Agusan del Sur Electric Cooperative, Inc. (ASELCO)12/20/201912/20/2019
2019-094 RCIn the Matter of the Application for the Approval of the Sale of Various Sub-Transmission Lines / Assets of the National Transmission Corporation (TRANSCO) to Cebu I Electric Cooperative, Inc. (CEBECO I), as Covered by a Contract to Sell dated 25 September 2019National Transmission Corporation (TRANSCO) and Cebu I Electric Cooperative, Inc. (CEBECO I)12/20/201912/20/2019
2019-093 RCIn the Matter of the Application for the Approval of the Implementation of the Lapu-lapu 230 KV Substation Project, with Prayer for Provisional Authority National Grid Corporation of the Philippines (NGCP)12/17/201912/17/2019
2019-092 RCIn the Matter of the Application for the Approval of the Implementation of the Cebu - Bohol 230 kV Interconnection Project, with Prayer for Provisional Authority National Grid Corporation of the Philippines (NGCP)12/17/201912/17/2019
2019-086 RCIn the Matter of the Application for the Approval of the Interim Maximum Annual Revenue for Calendar Year 2020, with Prayer for the Urgent Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP)10/29/201910/29/2019
2019-085 RCIn the Matter of the Application for the Approval of Force Majeure Event Regulated FM Pass-Through For Typhoon "Rosita" in Luzon, in Accordance with the Rules for Setting Transmission Wheeling Rates, with Prayer for Provisional Authority National Grid Corporation of the Philippines (NGCP)10/29/201910/29/2019
2019-077 RCIn the Matter of the Application for Approval of the Ancillary Services Procurement Agreement Between the National Grid Corporation of the Philippines and King Energy Generation, Inc. (Misamis Occidental Power Plant 2 - Panaon), with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP) and King Energy Generation, Inc. (KEGI) 10/15/201910/15/2019
2019-076 RCIn the Matter of the Application for Approval of the Ancillary Services Procurement Agreement Between the National Grid Corporation of the Philippines and King Energy Generation, Inc. (Misamis Occidental Power Plant 3 - Jimenez), with Prayer for the Issuance of Provisional Authority National Grid Corporation of the Philippines (NGCP) and King Energy Generation, Inc. (KEGI) 10/15/201910/15/2019
123

 TRANSMISSION SECTOR

Transmission Sector. The transmission of electric power shall be a regulated common electricity carrier business subject to the ratemaking powers of the ERC. (Sec. 7, RA 9136)

Creation of the National Transmission Company. The TRANSCO shall assume the authority of NPC for the planning, construction and centralized operation and maintenace of its high voltage transmission facilities, including grid interconnections and ancillary services. (Sec. 8, RA 9136)