Republic of the Philippines

ENERGY REGULATORY COMMISSION

A world class and independent electric power industry regulator that equitably promotes and protects the interests of consumers and other stakeholders, to enable the delivery of long-term benefits that contribute to sustained economic growth and an improved quality of life.



Promulgated Rules, Decisions and Orders


Initial Order, ERC Case No. 2021-002 RM, Petition for Rule-Change to Amend Resolution on the Recovery of Pass-Through Taxes (Real Property, Local Franchise, and Business Taxes) of Distribution Utilities Promulgated as ERC Resolution No. 02, Series Of 2021, Private Electric Power Operators Association (PEPOA) Applicant
Date Docketed:7/28/2021
Published: 7/28/2021




Resolution No. 07, Series of 2021, A Resolution Adopting Amendments to the Resolution No. 04, Series of 2017 Entitled "Amendments to the Pre-emptive Mitigating Measure in the Wholesale Electricity Spot Market (WESM)"
Date Docketed:7/28/2021
Published: 7/28/2021




Order, ERC Case No. 2021-042 RC, In the Matter of the Application for the Approval of the 20th Application for the Recovery of the Incremental Costs on Foreign Currency Exchange Rate Fluctuations Under the Incremental Currency Exchange Rate Adjustment, with Prayer for Provisional Authority (PA), National Power Corporation (NPC) applicant
Date Docketed:7/26/2021
Published: 7/26/2021


Order, ERC Case No. 2007-461 MC, In the Matter of Violation of ERC Order, Rules and Regulations (For: Non-Remittance of Proportionate Share in the Distribution Management Committee, Inc.), Cagayan de Sulu Electric Cooperative, Inc. (CASELCO) respondent
Date Docketed:7/26/2021
Published: 7/26/2021


Order, ERC Case No. 2018-012 SC, In Re: Violation of Article 5, Section 1 of ERC Resolution No. 21, Series of 2010 (Filing of Consolidated Applications), Panay Electric Company, Inc. (PECO) respondent
Date Docketed:7/26/2021
Published: 7/26/2021




Order, ERC Case No. 2016-002 RM, In the Matter of Petition to Initial Rule-Making for the Amendment of ERC Resolution No. 14, Series of 2015, Entitled “Resolution Adopting the Wind Feed-In Tariff (Wind FIT2) Rate, with Motion for Confidential Treatment of Information, Alternergy Wind One Corporation (AWOC), Petrowind Energy, Inc. (PWEI) and Trans-Asia Renewable Energy Corporation (TAREC) petitioners
Date Docketed:7/26/2021
Published: 7/26/2021


Order, ERC Case No. 2021-016 RC, In the Matter of the Application for Authority to Implement Microgrid Projects in Unviable Areas in the Municipality of Looc, Occidental Mindoro and Approval of Full Cost Recovery Rate (FCRR) Therefor with Urgent Prayer for Issuance of Provisional Authority, Lubang Electric Cooperative Inc. (LUBELCO) Applicant
Date Docketed:7/26/2021
Published: 7/26/2021


Order, ERC Case No. 2021-029 RC, In the Matter of the Application for Approval of the Power Supply Agreement (PSA) Entered Into By and Between Ifugao Electric Cooperative, Inc. and the Provincial Government of Ifugao (PGI), Ifugao Electric Cooperative, Inc. (IFELCO), and The Provincial Government of Ifugao (PGI) applicants
Date Docketed:7/23/2021
Published: 7/23/2021


Order, ERC Case No. 2004-451, In the Matter of the Application for Approval of the Business Separation and Unbundling Plan (BSUP) Pursuant to the Provision of Republic Act No. 9136, Ibaan Electric and Engineering Corporation (IEEC) applicant
Date Docketed:7/19/2021
Published: 7/19/2021


Decision, ERC Case No. 2007-410 MC, In the Matter of Violation of ERC Orders, Rules and Regulations, Siasi Electric Cooperative, Inc. (SIASELCO) respondent
Date Docketed:7/19/2021
Published: 7/19/2021

12345678910...>>

WORKS IN PROGRESS

CaseNoTitleApplicantDate PostedDate Docketed
2021-060 RCIn the Matter of the Application for Authority to Implement the Proposed Capital Expenditure Program for Regulatory Year (RY) 2022, with Prayer for Provisional Authority Manila Electric Company (MERALCO)7/26/20217/26/2021
2021-057 RCIn the Matter of the Application for the Approval of the Power Supply Agreement Between SN Aboitiz Power–Benguet, Inc. and Nueva Ecija 1 Electric Cooperative, Inc., with Motion for Confidential Treatment of Information and Prayer for Provisional Authority SN Aboitiz Power–Benguet, Inc. (SNAP-BI) and Nueva Ecija 1 Electric Cooperative, Inc, (NEECO I) 7/19/20217/19/2021
2021-055 RCIn the Matter of the Application for Approval of the 5 MW Emergency Power Supply Agreement Between Occidental Mindoro Electric Cooperative, Inc. and Occidental Mindoro Consolidated Power Corporation, with Prayer for Provisional Authority (PA)Occidental Mindoro Electric Cooperative, Inc. (OMECO) and Occidental Mindoro Consolidated Power Corporation (OMCPC) 7/19/20217/19/2021
2021-054 RCIn the Matter of the Application for Approval of the 20 MW Emergency Power Supply Agreement Between Occidental Mindoro Electric Cooperative, Inc. and Occidental Mindoro Consolidated Power Corporation, with Prayer for Provisional Authority (PA)Occidental Mindoro Electric Cooperative, Inc. (OMECO) and Occidental Mindoro Consolidated Power Corporation (OMCPC) 7/19/20217/19/2021
2021-053 RCIn the Matter of Application for the Approval of the 21st Generation Rate Adjustment Mechanism (21st GRAM), with Prayer for Provisional Authority (PA)National Power Corporation (NPC)7/19/20217/19/2021
2021-052 RCIn the Matter of the Application for Authority to Retire the Tanza Substation Located at Barangay Amaya VI, Antero Soriano Highway, Tanza, Cavite and to Withdraw from Service Certain Equipment and Machinery Installed in said Substation, with Prayer for Provisional Authority Manila Electric Company (MERALCO)7/19/20217/19/2021
2021-050 RCIn the Matter of the Application for the Approval of the Proposed Capital Expenditure Projects for the Years 2019 - 2021 with Application for Authority to Secure Loan from the National Electrification Administration (NEA) and/or Private Financial Institution Zamboanga City Electric Cooperative, Inc. (ZAMCELCO)7/8/20217/8/2021
2021-048 RC In the Matter of the Joint Application for the Approval of the Electric Power Purchase Agreement Entered Into by and Between La Union Electric Company, Inc. and Masinloc Power Partners Co. Ltd., with Motion for the Issuance of a Provisional Authority or Interim Relief and Confidential Treatment of Information La Union Electric Company, Inc. (LUECO) and Masinloc Power Partners Co., Ltd. (MPPCL)7/7/20217/7/2021
2021-047 RC In the Matter of the Application for the Approval of the Power Supply Agreement Between Subic Enerzone Corporation SEZ) and Masinloc Power Partners Co. Ltd., (MPPCL) with Motion or Confidential Treatment of Information and Prayer for Provisional Authority or Interim ReliefSubic Enerzone Corporation (SEZ) and Masinloc Power Partners Co. Ltd. (MPPCL)6/21/20216/21/2021
2021-046 RC In the Matter of the Joint Application for Approval of the Power Supply Agreement Entered Into by and Between Nueva Ecija II Electric Cooperative, Inc. - Area 2 and Masinloc Power Partners Co. Ltd., with Prayer for Provisional Authority and/or Interim Relief and Confidential Treatment of Information Nueva Ecija II Electric Cooperative, Inc. Area 2 (NEECO II – Area 2) And Masinloc Power Partners Co., Ltd. (MPPCL)6/16/20216/16/2021
12345

 DISTRIBUTION SECTOR

Distribution Sector. The distribution of electricity to end-users shall be a regulated common carrier business requiring a national franchise. Distribution of electric power to all end-users may be undertaken by private distribution utilities, cooperatives, local government units presently undertaking this function and other duly authorized entities, subject to regulation by the ERC. (Sec. 22, RA 9136)

Distribution Utility refers to any electric cooperative, private corporation, government-owned utility or existing local government unit which has an exclusive franchise area to operate a distribution system in accordance with this Act. (Sec. 4 q, RA 9136) Utilities, including grid interconnections and ancillary services. (Sec. 8, RA 9136)

Downloadable Files

DISTRIBUTION UTILITY MAP

   

 


© 2021 - Energy Regulatory Commission