Republic of the Philippines

ENERGY REGULATORY COMMISSION

A world class and independent electric power industry regulator that equitably promotes and protects the interests of consumers and other stakeholders, to enable the delivery of long-term benefits that contribute to sustained economic growth and an improved quality of life.


Documentary requirements for the issuance of COC

1. Entities with Self-Generating Facilities (SGFs) with less than 1 MW aggregate installed capacity
Form 1 - Application for COC

Form 2 - Company Profile

2. Entities with Self-Generating Facilities (SGFs) with 1 MW and above aggregate installed capacity
Form 1 - Application for COC
Form 2 - Company Profile
Form 3 - Five-Year Operational History

Other Documentary requirements (SEC Registration, Articles of Incorporation, General Information Sheet (SEC Form), DOE/ NPC Cetificate of Accreditation if applicable, and DENR - ECC/ PTO

3. Independent Power Producer/ DU owned Power Plant Form
Form 1 - Application for COC
Form 2 - Company Profile
Form 3 - Five -Year Operational History
Form 4 - Affidavit of Compliance with PGC and PDC
Form 5 - Affidavit of Compliance with WESM Rules
Form 6 - Affidavit of Compliance with Cross Ownership and Market Share Restrictions
Form 7
4. Interim Mindanao Electricity Market (IMEM) New COC Applications
Form 1 - Application for COC (IMEM)
Form 2 - Company Profile
Form 3 - Five-Year Operational History
Form 4 - Affidavit of Compliance with PGC and PDC
Form 5 - Affidavit of Compliance with WESM Rules
Form 6 - Affidavit of Compliance with Cross Ownership and Market Share Restrictions
Form 7 - General Plant Description

 

Today at ERC
Thursday, November 21, 2019

Hearing Schedules
Time:
10:00
Case No.:
2019-068 RC [JU] [EX] [PT] [EV]
Applicant:
IEC
Venue:
IEC’s Principal Office, Metro-Rei Business Park, Brgy. Palindan, Ibaan, Batangas
Title:
In the Matter of the Application for the Approval of the Capital Expenditure Projects of Ibaan Electric Corporation (IEC) for the Years 2013 to 2018
Time:
10:00
Case No.:
2019-072 RC [JU] [EX] [PT] [EV]
Applicant:
ANECO
Venue:
ANECO's Main Office, Km. 2, J. C. Aquino Avenue, Butuan City, Agusan del Norte
Title:
In the Matter of the Application for the Approval of the Generation Rate for the Use (Acquisition and Operation) of Five (5) Units of Two (2) MW Modular Generation Sets and the Corresponding Loan from the National Electrification Administration (NEA)
Time:
14:00
Case No.:
2018-014 MC [EV]
Applicant:
NGCP
Venue:
ERC Hearing Room (15th floor)
Title:
Petition for the Approval of the Extension of the Period for Listing of the Shares of Stock of the National Grid Corporation of the Philippines
Time:
14:00
Case No.:
2019-025 MC [JU] [EX] [PT] [EV]
Applicant:
ELPI
Venue:
ERC Hearing Room (15th floor)
Title:
In the Matter of the Application for Authority to Develop, Own and Operate a Dedicated Point-to- Point Limited Transmission Facilities to Connect the 100MW Pasuquin Solar Power Plant to the National Grid Corporation of the Philippines Laoag 115 KV Substation, with Prayer for Provisional Authority