Notice of Proposed Rule-Making and RULES for Setting the EC's Wheeling Rates
Notice is hereby given that on March 25, 2009, the General Managers of all the on-grid Electric Cooperatives (ECs) in the Philippines adopted Resolution No. 1, Series of 2009, entitled “A Resolution Imploring Upon The Energy Regulatory Commission (ERC) To Implement A New Rate-Setting and “Benchmarking” Methodology For Setting The Electric Cooperatives’ Wheeling Rates”.
The Commission has set this rule-making petition for public hearings on the following dates and venues:
ELECTRIC COOPERATIVES |
DATE |
TIME |
VENUE |
| ABRA (ABRECO) | May 20, 2009 |
9:00 AM |
ABRECO's Main Office, Bangued, Abra |
| AGUSAN DEL NORTE (ANECO) | July 2, 2009 |
9:00 AM |
ANECO's Main Office, Km. 2 J. C. Aquino Avenue, Butuan City, Agusan del Norte |
| AGUSAN SUR (ASELCO) | July 1, 2009 |
9:00 AM |
ASELCO's Main Office, San Isidro, San Francisco, Agusan del Sur |
| AKLAN (AKELCO) | June 30, 2009 |
2:00 PM |
AKELCO's Main Office, Lezo, Kalibo, Aklan |
| ALBAY (ALECO) | May 19, 2009 |
2:00 PM |
ALECO's Main Office, W. Vinzons St., Albay District, Legazpi City, Albay |
| ANTIQUE (ANTECO) | July 2, 2009 |
9:00 AM |
ANTECO's Main Office, Brgy. Funada, San Jose de Buenavista, Antique |
| AURORA (AURELCO) | June 16, 2009 |
9:00 AM |
AURELCO's Main Office, Brgy. Reserva, Baler, Aurora |
| BATANGAS I (BATELEC I) | July 14, 2009 |
2:00 PM |
BATELEC I's Main Office, Calaca, Batangas |
| BATANGAS II (BATELEC II) | July 15, 2009 |
9:00 AM |
BATELEC II's Main Office, Antipolo del Norte, Lipa City |
| BENGUET (BENECO) | May 20, 2009 |
9:00 AM |
BENECO's Main Office, Alapang, La Trinidad, Benguet |
| BILIRAN (BILECO) | June 23, 2009 |
9:00 AM |
BILECO's Main Office, Caray-caray, Naval, Biliran, Leyte |
| BOHOL I (BOHECO I) | June 17, 2009 |
9:00 AM |
BOHECO I's Main Office, Maca-as, Tubigon, Bohol |
| BOHOL II (BOHECO II) | June 18, 2009 |
9:00 AM |
BOHECO II's Main Office, Cantagay, Jagna, Bohol |
| BUKIDNON I (FIBECO) | June 30, 2009 |
9:00 AM |
FIBECO's Main Office, Anahawon, Maramag, Bukidnon |
| BUKIDNON II (BUSECO) | July 1, 2009 |
9:00 AM |
BUSECO's Main Office, Manolo Fortich, Bukidnon |
| CAGAYAN I (CAGELCO I) | July 14, 2009 |
2:00 PM |
CAGELCO I's Main Office, Maddarulug, Solana, Cagayan Valley |
| CAGAYAN II (CAGELCO II) | July 17, 2009 |
9:00 AM |
CAGELCO II's Main Office, Maharlika Highway, Macanaya District, Aparri, Cagayan Valley |
| CAMARINES NORTE (CANORECO) | July 1, 2009 |
2:00 PM |
CANORECO's Main Office, Jose P. Rizal St., Daet, Camarines Norte |
| CAMARINES SUR I (CASURECO I) | July 2, 2009 |
9:00 AM |
CASURECO I's Main Office, Puro-Batia, Libmanan, Camarines Sur |
| CAMARINES SUR II (CASURECO II) | June 30, 2009 |
2:00 PM |
CASURECO II's Main Office, Brgy. Del Rosario, Naga City, Camarines Sur |
| CAMARINES SUR III (CASURECO III) | June 4, 2009 |
2:00 PM |
CASURECO III's Main Office, San Isidro, Iriga City, Camarines Sur |
| CAMARINES SUR IV (CASURECO IV) | June 3, 2009 |
2:00 PM |
CASURECO IV's Main Office, Talojongon, Tigaon, Camarines Sur |
| CAMIGUIN (CAMELCO) | July 3, 2009 |
9:00 AM |
CAMELCO's Main Office, Capitol Hills, Pandan, Mambajao, Camiguin, Misamis Oriental |
| CAPIZ (CAPELCO) | July 1, 2009 |
9:00 AM |
CAPELCO's Main Office, Brgy. Timpas, Panitan, Capiz |
| CEBU I (CEBECO I) | May 29, 2009 |
9:00 AM |
CEBECO I's Main Office, Bito-on, Dumanjug, Cebu |
| CEBU II (CEBECO II) | May 28, 2009 |
9:00 AM |
CEBECO II's Main Office, Malingin, Bogo, Cebu |
| CEBU III (CEBECO III) | May 27, 2009 |
9:00 AM |
CEBECO III's Main Office, Luray II, Toledo City |
| CENTRAL NEGROS (CENECO) | June 3, 2009 |
9:00 AM |
CENECO's Main Office, Cor. Gonzaga & Mabini Steets, Bacolod City |
| CENTRAL PANGASINAN (CENPELCO) | July 15, 2009 |
9:00 AM |
CENPELCO's Main Office, Padilla Street, San Carlos City, Pangasinan |
| DAVAO NORTE (DANECO) | May 29, 2009 |
9:00 AM |
DANECO's Main Office, Km. 100 Montevista, Compostella Valley, Tipaz District, Tagum City |
| DAVAO ORIENTAL (DORECO) | May 28, 2009 |
9:00 AM |
DORECO's Main Office, Madang Hi-Way, Mati, Davao Oriental |
| DAVAO SUR (DASURECO) | June 11, 2009 |
9:00 AM |
DASURECO's Main Office, Cogon, Digos City, Davao del Sur |
| EASTERN SAMAR (ESAMELCO) | June 23, 2009 |
2:00 PM |
ESAMELCO's Main Office, Brgy. Cabong, Borongan, Eastern Samar |
| FIRST LAGUNA (FLECO) | May 28, 2009 |
9:00 AM |
FLECO's Main Office, Brgy. Lewin, Lumban, Laguna |
| GUIMARAS (GUIMELCO) | June 16, 2009 |
2:00 PM |
GUIMELCO's Main Office, San Miguel, Jordan, Guimaras |
| IFUGAO (IFELCO) | May 22, 2009 |
9:00 AM |
IFELCO's Main Office, Rizal Avenue, Poblacion, Lagawe, Ifugao |
| ILOCOS NORTE (INEC) | May 19, 2009 |
9:00 AM |
INEC's Main Office, Brgy. Suyo, Dingras, Ilocos Norte |
| ILOCOS SUR (ISECO) | May 21, 2009 |
9:00 AM |
ISECO's Main Office, Bigbiga, Santiago, Ilocos Sur |
| ILOILO I (ILECO I) | June 19, 2009 |
9:00 AM |
ILECO I's Main Office, Brgy. Namucon, Tigbauan, Iloilo |
| ILOILO II (ILECO II) | June 17, 2009 |
2:00 PM |
ILECO II's Main Office, Brgy. Cau-ayan, Pototan, Iloilo |
| ILOILO III (ILECO III) | June 18, 2009 |
9:00 AM |
ILECO III's Main Office, Brgy. Preciosa, Sara, Iloilo |
| ISABELA I (ISELCO I) | June 3, 2009 |
9:00 AM |
ISELCO I's Main Office, Victoria, Alicia, Isabela |
| ISABELA II (ISELCO II) | June 2, 2009 |
2:00 PM |
ISELCO II's Main Office, Alibagu, Ilagan, Isabela |
| KALINGA-APAYAO (KAELCO) | July 15, 2009 |
9:00 AM |
KAELCO's Main Office, Purok 5, Provincial Road, Bulanao, Tabuk, Kalinga-Apayao |
| LA UNION (LUELCO) | May 19, 2009 |
9:00 AM |
LUELCO's Main Office, Sta. Rita East, Aringay, La Union |
| LANAO NORTE (LANECO) | June 10, 2009 |
9:00 AM |
LANECO's Main Office, Tubod, Lanao del Norte |
| LEYTE I (LEYECO I/DORELCO) | June 25, 2009 |
9:00 AM |
LEYECO I's Main Office, Brgy. San Roque, Tolosa, Leyte |
| LEYTE II (LEYECO II) | June 26, 2009 |
9:00 AM |
LEYECO II's Main Office, Real St., Sagkahan District, Tacloban City |
| LEYTE III (LEYECO III) | June 24, 2009 |
9:00 AM |
LEYECO III's Main Office, Brgy. San Roque, Tunga, Leyte |
| LEYTE IV (LEYECO IV) | June 10, 2009 |
9:00 AM |
LEYECO IV's Main Office, Brgy. Lamak, Hilongos, Leyte |
| LEYTE V (LEYECO V) | June 9, 2009 |
9:00 AM |
LEYECO V's Main Office, Brgy. San Pablo, Ormoc City |
| MAGUINDANAO (MAGELCO) | June 9, 2009 |
9:00 AM |
MAGELCO's Main Office, Awang, Dinaig, Maguindanao |
| MISAMIS OCCIDENTAL I (MOELCI I) | July 8, 2009 |
9:00 AM |
MOELCI I's Main Office, Macamiguing, Calamba, Misamis Occidental |
| MISAMIS OCCIDENTAL II (MOELCI II) | July 9, 2009 |
9:00 AM |
MOELCI II's Main Office, Don Anselco Bernad Ave., Bitoon, Ozamis City, Misamis Occidental |
| MISAMIS ORIENTAL I (MORESCO I) | June 9, 2009 |
9:00 AM |
MORESCO I's Main Office, Laguindingan, Misamis Oriental |
| MISAMIS ORIENTAL II (MORESCO II) | July 2, 2009 |
9:00 AM |
MORESCO II's Main Office, Medina, Misamis Oriental |
| MT. PROVINCE (MOPRECO) | May 21, 2009 |
9:00 AM |
MOPRECO's Main Office, Poblacion, Bontoc, Mt. Province |
| NEGROS OCCIDENTAL (NOCECO) | June 2, 2009 |
9:00 AM |
NOCECO's Main Office, Naga, Kabankalan City, Negros Occidental |
| NEGROS ORIENTAL I (NORECO I) | June 24, 2009 |
9:00 AM |
NORECO I's Main Office, Tinaogan, Bindoy, Negros Oriental |
| NEGROS ORIENTAL II (NORECO II) | June 25, 2009 |
9:00 AM |
NORECO II's Main Office, Real St., Dumaguete City, Negros Oriental |
| NORTH COTABATO (COTELCO) | June 10, 2009 |
9:00 AM |
COTELCO's Main Office, Manubuan, Matalam, Cotabato |
| NORTHERN SAMAR (NORSAMELCO) | June 26, 2009 |
9:00 AM |
NORSAMELCO's Main Office, Catarman, Northern Samar |
| NUEVA ECIJA I (NEECO I) | June 19, 2009 |
2:00 PM |
NEECO I's Main Office, Malapit, San Isidro, Nueva Ecija |
| NUEVA ECIJA II (NEECO II) Area I | June 18, 2009 |
9:00 AM |
NEECO II-Area I's Main Office, Calipahan, Talavera, Nueva Ecija |
| NUEVA ECIJA II (NEECO II) Area II | June 18, 2009 |
2:00 PM |
NEECO II-Area II's Main Office, San Leonardo, Nueva Ecija |
| NUEVA VIZCAYA (NUVELCO) | June 4, 2009 |
9:00 AM |
NUVELCO's Main Office, Gabut, Dupax del Sur, Nueva Viscaya |
| PAMPANGA I (PELCO I) | May 28, 2009 |
9:00 AM |
PELCO I's Main Office, Sto. Domingo, Mexico, Pampanga |
| PAMPANGA II (PELCO II) | May 27, 2009 |
9:00 AM |
PELCO II's Main Office, San Roque, Guagua, Pampanga |
| PAMPANGA III (PELCO III) | May 26, 2009 |
9:00 AM |
PELCO III's Main Office, Quintos Bldg., McArthur Highway San Vicente, Apalit, Pampanga |
| PAMPANGA RURAL (PRESCO) | July 16, 2009 |
9:00 AM |
PRESCO's Main Office, San Ros Subd., Ninoy Aquino By-Way, Brgy. Anao, Mexico Pampanga |
| PANGASINAN I (PANELCO I) | July 14, 2009 |
9:00 AM |
PANELCO I's Main Office, San Jose, Bani, Pangasinan |
| PANGASINAN III (PANELCO III) | July 16, 2009 |
9:00 AM |
PANELCO III's Main Office, Nancayasan, Urdaneta City, Pangasinan |
| PENINSULA (PENELCO) | June 2, 2009 |
9:00 AM |
PENELCO's Main Office, Roman Super Highway, Tuyo, Balanga City, Bataan |
| QUEZON I (QUEZELCO I) | May 26, 2009 |
9:00 AM |
QUEZELCO I's Main Office, Brgy. Pictol, Pitogo, Quezon |
| QUEZON II (QUEZELCO II) | May 27, 2009 |
9:00 AM |
QUEZELCO II's Main Office, Brgy. Gumian, Infanta, Quezon |
| QUIRINO (QUIRELCO) | July 16, 2009 |
9:00 AM |
QUIRELCO's Main Office, Aurora East, Diffun, Quirino |
| SAMAR I (SAMELCO I) | June 25, 2009 |
9:00 AM |
SAMELCO I's Main Office, Brgy. Carayman, Calbayog City, Samar |
| SAMAR II (SAMELCO II) | June 24, 2009 |
9:00 AM |
SAMELCO II's Main Office, Catbalogan, Samar |
| SAN JOSE CITY (SAJELCO) | June 17, 2009 |
9:00 AM |
SAJELCO's Main Office, Maharlika Highway, San Jose City, Nueva Ecija |
| SIARGAO (SIARELCO) | July 9, 2009 |
9:00 AM |
SIARELCO's Main Office, Catabaan, Dapa, Siargao Island, Surigao del Norte |
| SO. COTABATO I (SOCOTECO I) | July 8, 2009 |
9:00 AM |
SOCOTECO I's Main Office, Matulas, Koronadal City, South Cotabato |
| SO. COTABATO II (SOCOTECO II) | July 9, 2009 |
9:00 AM |
SOCOTECO II's Main Office, Jose P. Catolico Sr. Ave., Lagao, General Santos City, South Cotabato |
| SO. LEYTE (SOLECO) | June 11, 2009 |
9:00 AM |
SOLECO's Main Office, Nasaug, Maasin City, Southern Leyte |
| SORSOGON (SORECO I) | May 20, 2009 |
9:00 AM |
SORECO I's Main Office, Gulang-Gulang, Irosin, Sorsogon |
| SORSOGON (SORECO II) | May 21, 2009 |
9:00 AM |
SORECO II's Main Office, Buhatan, Sorsogon, Sorsogon |
| SULTAN KUDARAT (SUKELCO) | July 7, 2009 |
9:00 AM |
SUKELCO's Main Office,National Highway, Tacurong, Sultan Kudarat |
| SURIGAO NORTE (SURNECO) | July 7, 2009 |
2:00 PM |
SURNECO's Main Office, Corner Narciso & Espina Streets, Surigao City, Surigao del Norte |
| SURIGAO SUR I (SURSECO I) | May 27, 2009 |
9:00 AM |
SURSECO I's Main Office, San Fernando, Bislig City, Surigao del Sur |
| SURIGAO SUR II (SURSECO II) | July 3, 2009 |
9:00 AM |
SURSECO II's Main Office, Navales St., Tandag, Surigao del Sur |
| TARLAC I (TARELCO I) | July 15, 2009 |
9:00 AM |
TARELCO I's Main Office, Amacalan, Gerona, Tarlac |
| TARLAC II (TARELCO II) | July 14, 2009 |
9:00 AM |
TARELCO II's Main Office, San Nicolas, Concepcion, Tarlac |
| V-M-C RURAL (VRESCO) | June 4, 2009 |
9:00 AM |
VRESCO's Main Office, Crossing Tortosa, Manapla, Negros Occidental |
| ZAMBALES I (ZAMECO I) | June 4, 2009 |
9:00 AM |
ZAMECO I's Main Office, San Vicente, Palauig, Zambales |
| ZAMBALES II (ZAMECO II) | June 3, 2009 |
9:00 AM |
ZAMECO II's Main Office, Magsaysay, Castillejos, Zambales |
| ZAMBOANGA CITY (ZAMCELCO) | June 19, 2009 |
9:00 AM |
ZAMCELCO's Main Office, Putik Complex, Zamboanga City |
| ZAMBOANGA NORTE (ZANECO) | July 7, 2009 |
2:30 PM |
ZANECO's Main Office, Gen. Luna St., Dipolog City, Zamboanga del Norte |
| ZAMBOANGA SUR I (ZAMSURECO I) | June 18, 2009 |
9:00 AM |
ZAMSURECO I's Main Office, J. S. Alano St., Pagadian City, Zamboanga del Sur |
| ZAMBOANGA SUR II (ZAMSURECO II) | June 17, 2009 |
9:00 AM |
ZAMSURECO II's Main Office, Pangi, Ipil, Zamboanga del Sur |
The last public hearing is set on July 20, 2009 at two o’clock in the afternoon (2:00 P.M.) at the ERC Hearing Room, 15th Floor, Pacific Center Building, San Miguel Avenue, Pasig City.
All interested parties may submit their comments (in both hard and soft copies) on or before May 11, 2009. Electronic copies may be sent to tariffs@erc.gov.ph. Parties who have filed their written comments on or before this date shall be given priority during the above-scheduled public hearings. However, written comments submitted after this date but not later than fifteen (15) days from the date of the last scheduled hearing shall still be received to form part of the records and considered in any action to be taken on this petition.
Notice of Proposed Rule-Making
Rules for Setting the EC's Wheeling Rates
April 23, 2009