CAPEX PROJECTS - VISAYAS
SUMMARY SHEET
|
NAME OF PROJECTS |
STATUS/ RANK |
Cost Disbursement 2005-2010 (Millions) |
||
|
US$ |
PhP |
Total PhP |
||
|
Completed |
0.00 |
65.85 |
65.85 |
|
|
Completed |
0.00 |
11.80 |
11.80 |
|
|
Leyte-Luzon HVAC Interconnection
Project |
Completed |
0.00 |
11.60 |
11.60 |
|
Leyte-Samar Reinf.
69/138kV Project |
Completed |
0.52 |
127.61 |
156.90 |
|
Completed |
0.00 |
8.00 |
8.00 |
|
|
|
|
|
|
|
|
On-going |
0.00 |
212.07 |
212.07 |
|
|
On-going |
23.61 |
61.84 |
1,383.72 |
|
|
On-going |
42.29 |
583.53 |
2,951.75 |
|
|
On-going |
45.64 |
640.73 |
3,196.31 |
|
|
On-going |
0.13 |
15.72 |
23.00 |
|
|
On-going |
0.00 |
130.66 |
130.66 |
|
|
On-going |
42.35 |
369.65 |
2,741.22 |
|
|
On-going |
0.00 |
69.95 |
69.95 |
|
|
On-going |
0.00 |
146.96 |
146.96 |
|
|
On-going |
2.71 |
26.50 |
178.18 |
|
|
On-going |
8.60 |
330.50 |
811.83 |
|
|
|
|
|
|
|
|
1st Priority |
15.47 |
433.12 |
1,299.48 |
|
|
|
|
|
|
|
|
2nd Priority |
0.00 |
110.98 |
110.98 |
|
|
2nd Priority |
4.02 |
104.08 |
329.14 |
|
|
2nd Priority |
5.79 |
68.72 |
393.13 |
|
|
2nd Priority |
0.00 |
55.93 |
55.93 |
|
|
|
|
191.12 |
3,585.78 |
14,288.45 |