Notice of Public Hearing, ERC Case No. 2018-002 DR (anew)

 In the Matter of Dispute Resolution on Collection or Refund From Green Future Innovations Inc. (GFII) of Generation / Transmission Service Charges for October 2012 to August 2013 Bill Collected by National Grid Corporation of the Philippines  (NGCP) from Isabela II Electric Cooperative, Inc. (ISELCO II), Isabela II Electric Cooperative, Inc. (ISELCO II) petitioner versus Green Future Innovations Inc. (GFII) respondent

NOPH_ERC Case No. 2018-002 DR
Initial Order ERC Case No. 2018-002 DR

 

Today at ERC
Wednesday, March 20, 2019

Hearing Schedules
Time:
09:00
Case No.:
2018-048 RC [JU] [EX] [PT] [EV]
Applicant:
NPC
Venue:
NORSAMELCO's Main Office, Catarman, Northern Samar
Title:
In the Matter of the Petition for the Approval of the Proposed New Subsidized Approved Generation Rate (SAGR) with Prayer for Provisional Authority
Time:
10:00
Case No.:
2019-005 RC [JU] [EX] [PT] [EV]
Applicant:
MERALCO
Venue:
ERC Hearing Room (15th floor)
Title:
In the Matter of the Application for Approval of the Emergency Replacement of One (1) 33-MVA Power Transformer at Tagaytay Substation
Time:
14:00
Case No.:
2019-001 MC [JU] [EX] [PT] [EV]
Applicant:
BGI
Venue:
ERC Hearing Room (15th floor)
Title:
In the Matter of the Application for Authority to Develop, Own, and Operate Dedicated Point - to - Point Limited Facilities to Connect the Palayan Binary Power Plant Project to the Luzon Grid, with Prayer for Provisional Authority